back to portal home

Lots 17 - 29

When will my home be ready?

Civil construction

Complete

Home Construction

In progress

Estimated home construction completion timeframe

October 2024

Estimated Title Registration timeframe

October 2024

Estimated Settlement timeframe

November 2024

Comments

Home Construction Progress Video - September  2024

UPDATE - 1 October 2024

Welcome to the Coomoora Construction Update for September 2024!  Below you’ll find information about progress of your home and key next steps in construction.

The latest construction update video highlights the current progress of your home.

Our team is continuing to work with Creation Homes ahead of construction completion and settlement of your home.  As we are closer to completion, we have been able to revise the settlement timeframes for your home to align with the works being completed on site.

Please see below the current estimated settlement timeframes for your home. These will also be reflected on the Coomoora Connect portal shortly.

Lots 17 - 29
Estimated Settlement Timeframe – November 2024

Lots 30 - 34
Estimated Settlement Timeframe – November 2024

Lots 35 - 49
Estimated Settlement Timeframe – December 2024 - January 2025

Lots 50 - 63

** The current Estimated Settlement Timeframe remains as November - December 2024

Below is an update on the status of works and milestones on your townhome:

Lots 17 - 29

- Valuations, fencing and landscaping are nearing completion.
- Final preparations for pre-settlement inspections with purchasers are underway.

Lots 30 - 34

- Valuations, fencing and landscaping are nearing completion.
- Final preparations for pre-settlement inspections with purchasers are underway.

Lots 35 - 49

- Paving is complete.
- Valuations and fencing are nearing completion.
- Landscaping to continue through October.

Lots 50 - 63

- Paving is complete.
- Valuations and fencing are nearing completion.
- Landscaping to continue through October.


Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.

COMMON OPEN SPACE

While home construction is occurring, works on the common open space areas are continuing to progress well.

Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.

We hope this update has been helpful and look forward to bringing you our next update in late-October.

UPDATE - 6 August 2024

We are delighted to advise that your Coomoora home is now ready for bank valuation inspections.  

Valuation inspections can be undertaken by your bank-nominated valuer from Monday 12 August 2024 on Mondays and Wednesdays between 9am and 5pm.

The valuer or their representative must contact Al Bogdani (Sales Consultant) on 0409 632 895 or email al@rpmgrp.com.au and cc coomoora@development.vic.gov.au to book an appointment before they can conduct a valuation inspection.  

Alternatively, RPM can contact the valuer should you provide their details.

Please note that appointments are mandatory for the valuation inspections as this process will ensure that the builder can facilitate appropriate access to the construction site.

These inspections are restricted to the bank's valuer. You will be notified at a later date when homes will be ready for your pre-settlement inspections.

If at the time of your contract signing you had not nominated a conveyancer, please ensure you email these details as a matter of urgency.

Should you have any questions, please send an email to: coomoora@development.vic.gov.au

UPDATE - 3 August 2024

Welcome to the Coomoora Construction Update for August 2024!  Below you’ll find information about progress of your home and key next steps in construction.

Our team is continuing to work with Creation Homes ahead of construction completion and settlement of your home.  As we are closer to completion, we have been able to revise the timeframes for your home to align with the works being completed on site. Please see below the current estimated timeframes for your home. These will also be reflected on the Coomoora Connect portal shortly.

Lots 17 - 29

Estimated Home Construction Completion Timeframe – October 2024
Estimated Title Registration Timeframe – October 2024
Estimated Settlement Timeframe – October - November 2024



Lots 30 - 34

Estimated Home Construction Completion Timeframe – October 2024
Estimated Title Registration Timeframe – October 2024
Estimated Settlement Timeframe – October - November 2024

Lots 35 - 49
Estimated Home Construction Completion Timeframe – November 2024
Estimated Title Registration Timeframe – November 2024
Estimated Settlement Timeframe – November - December 2024

Lots 50 - 63

Estimated Home Construction Completion Timeframe – November 2024
Estimated Title Registration Timeframe – November 2024
Estimated Settlement Timeframe – November - December 2024

UPDATES TO COOMOORA CONNECT PORTAL

Development Victoria is committed to assisting their purchasers with a clear communication in the milestones that will occur in the upcoming months to your handover.

As the first step, we have completed some updates made to the Coomoora Connect portal.  This includes changes to the last milestones displayed on the “Home Construction Progress” bar chart.

As a separate feature of the updated Coomoora Connect portal, we have introduced the “Settlement and Handover Process” bar chart, which indicates the key milestones as part of your upcoming settlement and handover journey.

The new “Settlement and Handover Process” bar chart can be found on your respective lot group page and is displayed below. Please hover over the milestones for more details.

We will also be adding key information about your home to the “Key Documents” section on the Coomoora Connect portal. The first of these is the Development Plan for your information and a more detailed explanation of the Settlement and Handover Process. In the coming weeks, we will be sharing answers to some Frequently Asked Questions, so please keep an eye out.

Below is an update on the status of works and milestones on your townhome:

Lots 17 - 29 
Valuations are underway.
Fencing and landscaping to continue through September.

Lots 30 - 34
Valuations are underway.
Fencing and landscaping to continue through September.

Lots 35 - 49
Flooring is complete.
Valuations are underway.
Paving, fencing and landscaping to continue through September.

Lots 50 - 63
Valuations are underway.
Paving, fencing and landscaping to continue through September.


Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.

COMMON OPEN SPACE

While home construction is occurring, works on the common open space areas within Coomoora are continuing to progress. New footpaths have been laid, areas have been mulched and planting is underway.

Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.

We hope this update has been helpful and look forward to bringing you our next update in late-September.

UPDATE - 31 July 2024

Welcome to the Coomoora Construction Update for July 2024!  Below you’ll find information about progress of your home and key next steps in construction.

Creation Homes is continuing to make great progress on townhome construction, which is reflected in the below update on the status of works on all townhomes:

Lots 17-29

  • Fit-off and Paving are complete.
  • Fencing is nearing completion.
  • Landscaping to continue through August.

Lots 30-34

  • Fit-off and Paving are complete.
  • Fencing is nearing completion.
  • Landscaping to continue through August.

Lots 35-49

  • Painting, tiling and fit-off are nearing completion.
  • Flooring and Paving to continue through August.
  • Landscaping to follow.

Lots 50-63

  • Flooring is complete.
  • Fencing and Paving are nearing completion.
  • Landscaping to continue through August.

Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.

Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.

We hope this update has been helpful and look forward to bringing you our next update in August.

UPDATE - 28 June 2024

Welcome to the Coomoora Construction Update for June 2024!  Below you’ll find information about progress of your home and key next steps in construction.

Great progress continues to be made by Creation Homes on townhome construction, which is reflected in the below update on the status of works on all townhomes:

Lots 17 - 29

  • Paving is complete.
  • Fit-off is nearing completion.
  • Landscaping to continue through July.

Lots 30 - 34

  • Paving is complete.
  • Fit-off is nearing completion.
  • Landscaping to continue through July.

Lots 35 - 49

  • Painting, tiling and fit-off are nearing completion.
  • Flooring to continue through July.
  • Paving and landscaping to follow.

Lots 50 – 63

  • Fit-off is complete.
  • Flooring is nearing completion.
  • Paving and landscaping to continue through July.

Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.

Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.

We hope this update has been helpful and look forward to bringing you our next update in July.

Home Construction Progress Video May 2024.

UPDATE - 31 May 2024

Welcome to the Coomoora Construction Update for May 2024!  Below you’ll find information about progress of your home and key next steps in construction.

Creation Homes is continuing to make great progress on townhome construction, which is reflected in the latest video.

Below is an update on the status of works on all townhomes:

Lots 17 - 29

  • Flooring is complete.
  • Fit-off is nearing completion.
  • Landscaping to continue through June.

Lots 30 - 34

  • Painting and flooring are complete.
  • Fit-off is nearing completion.
  • Landscaping to continue through June.

Lots 35 - 49

  • Insulation and plaster installation are complete.
  • Painting, tiling, fit-off and flooring to continue through June.
  • Landscaping to follow.

Lots 50 - 63

  • Painting, waterproofing, and tiling are complete.
  • Fit-off and flooring to continue through June.
  • Landscaping to follow.

Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.

Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.

We hope this update has been helpful and look forward to bringing you our next update in June.

UPDATE - 28 March 2024

Welcome to the Coomoora Construction Update for March 2024.  Below you’ll find information about progress of your home and key next steps in construction.

Great progress continues to be made by Creation Homes on the construction of townhomes.

As briefly discussed recently with RPM Real Estate, the projects sales agent, the accelerated progress being made on site has led to the estimated timeframes for both construction completion and settlement being updated.

These revised timeframes, which are now available on the Coomoora Connect portal, are briefly outlined below for your reference:

Lots Expected Settlement Timeframe

17 - 29 September - October 2024

30 - 34 September - October 2024

35 - 49 November - December 2024

50 - 63 October - November 2024

Below is an update on the status of construction progress on all Coomoora townhomes:

Lots 17 - 29  

  • Waterproofing, tiling, and fit-off are nearing completion.
  • Flooring and caulking to continue through April.
  • Landscaping to follow.

Lots 30 - 34

  • Joinery complete.
  • Insulation, plaster installation, fix carpentry and painting are nearing completion.
  • Waterproofing and tiling to continue through April.

Lots 35 - 49  

  • Insulation, plaster installation, joinery and fix carpentry are nearing completion.
  • Painting, waterproofing, tiling and fit-off to continue through April.
  • Flooring to follow.

Lots 50 - 63

  • Painting, waterproofing and tiling are nearing completion.
  • Fit-Off to continue through April.
  • Flooring to follow.

Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.

UPDATE - 29 February 2024

Welcome to the Coomoora Construction Update for February 2024! Below you’ll find information about progress of your home and key next steps in construction.

Creation Homes continue to make great progress on the construction of townhomes.

Below is an update on the status of works on all townhomes:

Lots 17 - 29 

  • Painting is complete.
  • Waterproofing, tiling and fit-off are nearing completion.
  • Flooring to follow.

Lots 30 - 34

  • Cladding works are complete.
  • Insulation/plaster has commenced.
  • Joinery and fix carpentry (internal doors and mouldings) to follow.

Lots 35 - 49

  • Cladding works are complete.
  • Insulation/plaster installation nearing completion.
  • Joinery and fix carpentry to continue through March.

Lots 50 - 63

  • Joinery and fix carpentry are complete.
  • Painting, waterproofing and tiling to continue through March.
  • Fit-Off of plumbing and electrical fixtures to follow.

Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.

We hope this update has been helpful and look forward to bringing you our next update in March!

Civil Construction Progress Video December 2023  Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail. 

Civil Construction Progress Video August 2023  Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.

Civil Construction Progress Video May 2023  Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works. Home construction will commence after civil construction is completed.

Home Construction Progress

home construction commences
85% COMPLETE
home construction complete
slab
Concrete footings for base is poured.
frame
Construction and set-up of frame for approval by a building surveyor.
lock up
External wall cladding and roof covering is completed and external doors and external windows are fixed.
internal
fit out
All internal fittings including architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards are fitted or fixed into position, and flooring is laid.
landscaping
In Progress
Planting of street trees for nature strips and trees in common areas as appropriate and landscaping in and around properties.
Settlement and Handover
Refer to the ‘Settlement and Handover’ timeline below and attached in ‘Key Documents’.
Post Handover
Refer to the Handover Guide for more information.

Settlement & Handover Process

Valuation
Bank valuation organised via your bank and the sales agent
Pre-settlement Inspection
On site appointment with our sales agent to inspect your home prior to settlement
Settlement Date Confirmed
Email from our settlement team to your conveyancer advising settlement will occur in 14 days
Handover Date Confirmed
Phone call from our sales agent to schedule handover appointment with you
Getting Ready for Handover
Email from the Coomoora team with key information about the Coomoora development and organising your service connections
Pre-settlement review
Appointment with our sales agent to review progress of Pre-Settlement Inspection items
Settlement
Exchange of funds and ownership details
Handover
On site appointment with our sales agent to receive keys and an introduction to your home