Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works. Home construction will commence after civil construction is completed.
Comments
Civil Construction Progress Video August 2023 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.
UPDATE - 18 July 2023
Title Registration has been achieved on your lot at Coomoora Springvale South!
Development Victoria is in the process of notifying your conveyancer and preparations can be made for settlement by no later than Tuesday 1st August 2023.
If you have any questions about the above information, please send an email to Simran.randhawa@development.vic.gov.au
Civil Construction Progress Video May 2023 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.
Civil Construction Progress Video December 2022 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.
Civil Construction Progress Video August 2022 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.