Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works. Home construction will commence after civil construction is completed.
Comments
UPDATE - 28 March 2024
Welcome to the Coomoora Construction Update for March 2024. Below you’ll find information about progress of your home and key next steps in construction.
Great progress continues to be made by Creation Homes on the construction of townhomes.
As briefly discussed recently with RPM Real Estate, the projects sales agent, the accelerated progress being made on site has led to the estimated timeframes for both construction completion and settlement being updated.
These revised timeframes, which are now available on the Coomoora Connect portal, are briefly outlined below for your reference:
Lots Expected Settlement Timeframe
17 - 29 September - October 2024
30 - 34 September - October 2024
35 - 49 November - December 2024
50 - 63 October - November 2024
Below is an update on the status of construction progress on all Coomoora townhomes:
Lots 17 - 29
Lots 30 - 34
Lots 35 - 49
Lots 50 - 63
Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.
UPDATE - 29 February 2024
Welcome to the Coomoora Construction Update for February 2024! Below you’ll find information about progress of your home and key next steps in construction.
Creation Homes continue to make great progress on the construction of townhomes.
Below is an update on the status of works on all townhomes:
Lots 17 - 29
Lots 30 - 34
Lots 35 - 49
Lots 50 - 63
Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.
We hope this update has been helpful and look forward to bringing you our next update in March!
Civil Construction Progress Video December 2023 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.
Civil Construction Progress Video August 2023 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.
Civil Construction Progress Video May 2023 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.