back to portal home

Lots 35 - 49

When will my home be ready?

Civil construction

Complete

Home Construction

In progress

Estimated home construction completion timeframe

August - September 2024

Estimated Title Registration timeframe

October - November 2024

Estimated Settlement timeframe

November - December 2024

Comments

UPDATE - 28 March 2024

Welcome to the Coomoora Construction Update for March 2024.  Below you’ll find information about progress of your home and key next steps in construction. 

Great progress continues to be made by Creation Homes on the construction of townhomes.  

As briefly discussed recently with RPM Real Estate, the projects sales agent, the accelerated progress being made on site has led to the estimated timeframes for both construction completion and settlement being updated. 

These revised timeframes, which are now available on the Coomoora Connect portal, are briefly outlined below for your reference:

 Lots  Expected Settlement Timeframe

 17 - 29  September - October 2024

 30 - 34  September - October 2024

 35 - 49  November - December 2024

 50 - 63  October - November 2024


Below is an update on the status of construction progress on all Coomoora townhomes:

Lots 17 - 29    

  • Waterproofing, tiling, and fit-off are nearing completion.
  • Flooring and caulking to continue through April.
  • Landscaping to follow.


Lots 30 - 34 

  • Joinery complete. 
  • Insulation, plaster installation, fix carpentry and painting are nearing completion. 
  • Waterproofing and tiling to continue through April.


Lots 35 - 49    

  • Insulation, plaster installation, joinery and fix carpentry are nearing completion.
  • Painting, waterproofing, tiling and fit-off to continue through April. 
  • Flooring to follow.


Lots 50 - 63 

  • Painting, waterproofing and tiling are nearing completion. 
  • Fit-Off to continue through April. 
  • Flooring to follow.


Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.  

 

 

 

 

UPDATE - 29 February 2024

Welcome to the Coomoora Construction Update for February 2024! Below you’ll find information about progress of your home and key next steps in construction.

Creation Homes continue to make great progress on the construction of townhomes.

Below is an update on the status of works on all townhomes:

 

Lots 17 - 29   

  • Painting is complete.
  • Waterproofing, tiling and fit-off are nearing completion.
  • Flooring to follow.


Lots 30 - 34

  • Cladding works are complete.
  • Insulation/plaster has commenced.
  • Joinery and fix carpentry (internal doors and mouldings) to follow.


Lots 35 - 49

  • Cladding works are complete.
  • Insulation/plaster installation nearing completion.
  • Joinery and fix carpentry to continue through March.


Lots 50 - 63

  • Joinery and fix carpentry are complete.
  • Painting, waterproofing and tiling to continue through March.
  • Fit-Off of plumbing and electrical fixtures to follow.


Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.  


We hope this update has been helpful and look forward to bringing you our next update in March! 

 

 

 

 

 

 

 

Civil Construction Progress Video December 2023  Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.  

 

 

 

 

 

Civil Construction Progress Video August 2023  Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail. 

 

 

 

 

 

 

Civil Construction Progress Video May 2023  Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail. 

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works. Home construction will commence after civil construction is completed.

Home Construction Progress

home construction commences
45% COMPLETE
home construction complete
slab
Concrete footings for base is poured.
frame
Construction and set-up of frame for approval by a building surveyor.
lock up
In Progress
External wall cladding and roof covering is completed, flooring is laid and external doors and external windows are fixed.
internal
fit out
All internal fittings including architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards are fitted or fixed into position.
landscaping
Planting of street trees for nature strips and trees in common areas as appropriate and landscaping in and around properties.
practical
completion
All building work is either complete or close to completion, in accordance with the contract/agreement with the relevant authorities. Property is reasonably fit for occupation.
final inspection
Final visit by building inspectors to ensure all fittings, fixtures are complete, in good condition and built to the standard and specification as indicated in relevant contracts/agreement. Certificate of occupancy is issued.
handover
All works are finalised and ready to hand over to purchaser to move in.