Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works. Home construction will commence after civil construction is completed.
Comments
Home Construction Progress Video - September 2024
UPDATE - 1 October 2024
Welcome to the Coomoora Construction Update for September 2024! Below you’ll find information about progress of your home and key next steps in construction.
The latest construction update video highlights the current progress of your home.
Our team is continuing to work with Creation Homes ahead of construction completion and settlement of your home. As we are closer to completion, we have been able to revise the settlement timeframes for your home to align with the works being completed on site.
Please see below the current estimated settlement timeframes for your home. These will also be reflected on the Coomoora Connect portal shortly.
Lots 17 - 29
Estimated Settlement Timeframe – November 2024
Lots 30 - 34
Estimated Settlement Timeframe – November 2024
Lots 35 - 49
Estimated Settlement Timeframe – December 2024 - January 2025
Lots 50 - 63
** The current Estimated Settlement Timeframe remains as November - December 2024
Below is an update on the status of works and milestones on your townhome:
Lots 17 - 29
- Valuations, fencing and landscaping are nearing completion.
- Final preparations for pre-settlement inspections with purchasers are underway.
Lots 30 - 34
- Valuations, fencing and landscaping are nearing completion.
- Final preparations for pre-settlement inspections with purchasers are underway.
Lots 35 - 49
- Paving is complete.
- Valuations and fencing are nearing completion.
- Landscaping to continue through October.
Lots 50 - 63
- Paving is complete.
- Valuations and fencing are nearing completion.
- Landscaping to continue through October.
Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.
COMMON OPEN SPACE
While home construction is occurring, works on the common open space areas are continuing to progress well.
Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.
We hope this update has been helpful and look forward to bringing you our next update in late-October.
UPDATE - 16 August 2024
We are delighted to advise that your Coomoora home is now ready for bank valuation inspections.
Valuation inspections can be undertaken by your bank-nominated valuer from Monday 19 August 2024 on Mondays and Wednesdays between 9am and 5pm.
The valuer or their representative must contact Al Bogdani (Sales Consultant) on 0409 632 895 or email al@rpmgrp.com.au and cc coomoora@development.vic.gov.au to book an appointment before they can conduct a valuation inspection.
Alternatively, RPM can contact the valuer should you provide their details.
Please note that appointments are mandatory for the valuation inspections as this process will ensure that the builder can facilitate appropriate access to the construction site.
These inspections are restricted to the bank's valuer. You will be notified at a later date when homes will be ready for your pre-settlement inspections.
If at the time of your contract signing you had not nominated a conveyancer, please ensure you email these details as a matter of urgency.
Should you have any questions, please send an email to: coomoora@development.vic.gov.au
UPDATE - 3 August 2024
Welcome to the Coomoora Construction Update for August 2024! Below you’ll find information about progress of your home and key next steps in construction.
Our team is continuing to work with Creation Homes ahead of construction completion and settlement of your home. As we are closer to completion, we have been able to revise the timeframes for your home to align with the works being completed on site. Please see below the current estimated timeframes for your home. These will also be reflected on the Coomoora Connect portal shortly.
Lots 17 - 29
Estimated Home Construction Completion Timeframe – October 2024
Estimated Title Registration Timeframe – October 2024
Estimated Settlement Timeframe – October - November 2024
Lots 30 - 34
Estimated Home Construction Completion Timeframe – October 2024
Estimated Title Registration Timeframe – October 2024
Estimated Settlement Timeframe – October - November 2024
Lots 35 - 49
Estimated Home Construction Completion Timeframe – November 2024
Estimated Title Registration Timeframe – November 2024
Estimated Settlement Timeframe – November - December 2024
Lots 50 - 63
Estimated Home Construction Completion Timeframe – November 2024
Estimated Title Registration Timeframe – November 2024
Estimated Settlement Timeframe – November - December 2024
UPDATES TO COOMOORA CONNECT PORTAL
Development Victoria is committed to assisting their purchasers with a clear communication in the milestones that will occur in the upcoming months to your handover.
As the first step, we have completed some updates made to the Coomoora Connect portal. This includes changes to the last milestones displayed on the “Home Construction Progress” bar chart.
As a separate feature of the updated Coomoora Connect portal, we have introduced the “Settlement and Handover Process” bar chart, which indicates the key milestones as part of your upcoming settlement and handover journey.
The new “Settlement and Handover Process” bar chart can be found on your respective lot group page and is displayed below. Please hover over the milestones for more details.
We will also be adding key information about your home to the “Key Documents” section on the Coomoora Connect portal. The first of these is the Development Plan for your information and a more detailed explanation of the Settlement and Handover Process. In the coming weeks, we will be sharing answers to some Frequently Asked Questions, so please keep an eye out.
Below is an update on the status of works and milestones on your townhome:
Lots 17 - 29
Valuations are underway.
Fencing and landscaping to continue through September.
Lots 30 - 34
Valuations are underway.
Fencing and landscaping to continue through September.
Lots 35 - 49
Flooring is complete.
Valuations are underway.
Paving, fencing and landscaping to continue through September.
Lots 50 - 63
Valuations are underway.
Paving, fencing and landscaping to continue through September.
Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.
COMMON OPEN SPACE
While home construction is occurring, works on the common open space areas within Coomoora are continuing to progress. New footpaths have been laid, areas have been mulched and planting is underway.
Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.
We hope this update has been helpful and look forward to bringing you our next update in late-September.
UPDATE - 31 July 2024
Welcome to the Coomoora Construction Update for July 2024! Below you’ll find information about progress of your home and key next steps in construction.
Creation Homes is continuing to make great progress on townhome construction, which is reflected in the below update on the status of works on all townhomes:
Lots 17-29
Lots 30-34
Lots 35-49
Lots 50-63
Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.
Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.
We hope this update has been helpful and look forward to bringing you our next update in August.
UPDATE - 28 June 2024
Welcome to the Coomoora Construction Update for June 2024! Below you’ll find information about progress of your home and key next steps in construction.
Great progress continues to be made by Creation Homes on townhome construction, which is reflected in the below update on the status of works on all townhomes:
Lots 17 - 29
Lots 30 - 34
Lots 35 - 49
Lots 50 – 63
Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.
Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.
We hope this update has been helpful and look forward to bringing you our next update in July.
Home Construction Progress Video May 2024.
UPDATE - 31 May 2024
Welcome to the Coomoora Construction Update for May 2024! Below you’ll find information about progress of your home and key next steps in construction.
Creation Homes is continuing to make great progress on townhome construction, which is reflected in the latest video.
Below is an update on the status of works on all townhomes:
Lots 17 - 29
Lots 30 - 34
Lots 35 - 49
Lots 50 - 63
Please note, as townhomes are currently under construction, access to lots during this time is not permitted due to safety reasons.
Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.
We hope this update has been helpful and look forward to bringing you our next update in June.
UPDATE - 28 March 2024
Welcome to the Coomoora Construction Update for March 2024. Below you’ll find information about progress of your home and key next steps in construction.
Great progress continues to be made by Creation Homes on the construction of townhomes.
As briefly discussed recently with RPM Real Estate, the projects sales agent, the accelerated progress being made on site has led to the estimated timeframes for both construction completion and settlement being updated.
These revised timeframes, which are now available on the Coomoora Connect portal, are briefly outlined below for your reference:
Lots Expected Settlement Timeframe
17 - 29 September - October 2024
30 - 34 September - October 2024
35 - 49 November - December 2024
50 - 63 October - November 2024
Below is an update on the status of construction progress on all Coomoora townhomes:
Lots 17 - 29
Lots 30 - 34
Lots 35 - 49
Lots 50 - 63
Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.
UPDATE - 29 February 2024
Welcome to the Coomoora Construction Update for February 2024! Below you’ll find information about progress of your home and key next steps in construction.
Creation Homes continue to make great progress on the construction of townhomes.
Below is an update on the status of works on all townhomes:
Lots 17 - 29
Lots 30 - 34
Lots 35 - 49
Lots 50 - 63
Should you have any enquiries about the above information, please send an email to: coomoora@development.vic.gov.au.
We hope this update has been helpful and look forward to bringing you our next update in March!
Civil Construction Progress Video December 2023 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.
Civil Construction Progress Video August 2023 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.
Civil Construction Progress Video May 2023 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.